June 10, 2019| Blog
Progress continues towards our dedicated ice efforts! Here’s the latest on what we’ve been up to: We soared past the million...
April 24, 2019| Blog
Progress continues at Enterprise! New updates: Seismic upgrade complete Interior framing complete Upgraded high-efficiency light fixture...
March 21, 2019| Blog
Construction is starting to pick up this month. We officially signed our contract with Expericon as our general contractor and...
January 11, 2019| Blog
After a bit of a holiday lull, we’re starting to see some forward progress on the construction front. We’ve received approval...
October 30, 2018| Blog
We are very happy to announce that SFBACC has received a grant from the USA Curling Darwin Curtis Fund, toward the construction of our...
September 22, 2018| Blog
SFBACC is excited to announce that we have received final architectural plans for our new dedicated curling facility, submitted our...
July 28, 2018| Blog
We’re thrilled to announce a founding sponsorship from Merrill Lynch Wealth Management, supporting curling development in the Bay...
July 12, 2018| Blog
Here is an update on the current schedule drivers, with some budget and fundraising notes as well: Building permit (City of Oakland) We...
June 29, 2018| Blog
We’re extremely happy to announce that SFBACC has been chosen as a grant recipient by the Olympic Club Foundation, supporting our...
June 16, 2018| Blog
The Dedicated Ice steering committee and sub-committees are pushing hard for a late-September/early October opening! Here’s what...